Activities |
.... |
Responsible partner |
...... |
Status |
| |
|
Preparatory actions, elaboration of management plans and/or of action plans
|
|
|
|
|
| A1 |
|
Stakeholder mapping and current situation analysis
|
|
Nature Conservation Agency |
|
Completed |
| A2 |
|
Elaboration of Project Communication Strategy
|
|
Nature Conservation Agency |
|
Completed |
| A3 |
|
Criteria for classification of degraded peatlands and optimal management approach definition
|
|
LSFI "Silava" |
|
Completed |
| A4 |
|
Approbation of the methodology for GHG emission accounting
|
|
LSFI "Silava" |
|
Completed |
| A5 |
|
Inventory of degraded peatland areas and development of database
|
|
Association "Baltic Coasts" |
|
Completed |
| A6 |
|
Elaboration of the Management Plan, Detail and Technical Designs
|
|
Association "Baltic Coasts" |
|
Completed |
| |
|
Development of peatland re-use optimisation model
|
|
|
|
|
| C1 |
|
Development of peatland re-use optimisation model - Stage I - Assessment of key processes in demo-sites
|
|
Nature Conservation Agency |
|
Completed |
| C2 |
|
Development of peatland re-use optimisation model - Stage II - Economic assessment of ecosystem services in demo-sites
|
|
Nature Conservation Agency |
|
Completed |
| C3 |
|
Development of peatland re-use optimisation model - Stage III - Assessment of the land use scenarios for demo-sites
|
|
Association "Baltic Coasts" |
|
Completed |
| C4 |
|
Testing of the peatland re-use optimisation model - Implementation of the land use scenarios in demo-sites
|
|
Nature Conservation Agency |
|
Completed |
| C5 |
|
LIFE Recommendations for multi-purpose application of support tools for management and re-use of degraded peatlands
|
|
Latvian Peat Association |
|
Completed |
| |
|
Monitoring of the impact of the project actions
|
|
|
|
|
| D1 |
|
Monitoring of the impact of project actions
|
|
LSFI "Silava" |
|
Completed |
| D2 |
|
Monitoring of the socio-economic impact of project
|
|
Nature Conservation Agency |
|
Completed |
| |
|
Public awareness and dissemination of results
|
|
|
|
|
| E1 |
|
Project website
|
|
Nature Conservation Agency |
|
Completed |
| E2 |
|
Public information and education materials
|
|
Nature Conservation Agency |
|
Completed |
| E3 |
|
Public information and education events
|
|
Nature Conservation Agency |
|
Completed |
| E4 |
|
Networking with other LIFE and non-LIFE projects
|
|
Nature Conservation Agency |
|
Completed |
| E5 |
|
Manual "Sustainable and Responsible After-use of Peat Extraction Areas"
|
|
Association "Baltic Coasts" |
|
Completed
|
| E6 |
|
International Conference about the degraded peatland management and re-use
|
|
Nature Conservation Agency |
|
Completed |
| E7 |
|
Layman's report
|
|
Nature Conservation Agency |
|
Completed |
| |
|
Overall project operation and monitoring
|
|
|
|
|
| F1 |
|
Project management
|
|
Nature Conservation Agency |
|
Completed |
| F2 |
|
Audit
|
|
Nature Conservation Agency |
|
Completed |
| F3 |
|
Compilation of information for indicator tables
|
|
Nature Conservation Agency |
|
Completed |
| F4 |
|
After-LIFE Plan |
|
Nature Conservation Agency |
|
Completed |